SUMMARY OF FINDINGS FROM SURVEY OF TOWNS

USING DEVELOPMENT REVIEW BOARDS

 

 

In November of 2004, I was asked to undertake a telephone survey of ten communities that had opted to establish Development Review Boards to handle development review responsibilities under Vermont’s Planning Law, 24 V.S.A., Chapter 117.  The study was requested by the Hinesburg Development Review Board (DRB) as input to an internal review of possible ways that its operations could be further improved.

 

Out of the 43 Vermont Cities, Towns, and Villages that have adopted the Development Review Board approach, a total of ten communities were selected for this study.  Selection criteria included location in or near Chittenden County, size ranging from slightly smaller than Hinesburg to slightly larger, and a reasonable length of experience with the DRB.  The following table shows the ten communities selected.

 

DRB TOWN SELECTION TABLE

 

 

 

 

 

 

2003 Pop.

2003 Permits

Last Zoning

Select?

Town

Estimate

Permits/Units

Update

Y/N

Colchester

17176

35/58

8/13/04

Y

Hinesburg

4427

19/19

9/17/04

 

Jericho

5066

14/14

1/21/03

Y

Milton

9924

67/95

6/07/04

Y

South Burlington

14946

132/132

4/06/04

Y

Williston

8156

46/47

6/07/04

Y

Enosburg  Falls (Vill.)

na

na

9/14/04

Y

St. Albans Town

5718

35/58

7/19/04

Y

Grand Isle

2194

25/41

12/04/03

Y

Hyde park

3015

28/28

06/04/03

Y

Morrisville/Morristown

6447

38/44

02/03/04

Y

 

 

A series of questions was developed, based on discussions with Hinesburg staff and observation of a DRB meeting.  This was reviewed with the Hinesburg Planner before being used to guide the interviews.  Since the interviews were to be conducted by telephone, it was not necessary to create a formal, self guiding questionnaire instrument.  A copy of the list of questions is attached as an appendix to this report.  The list includes questions to determine background and history with the DRB, questions of staffing and staff responsibilities, questions relating to meeting procedures, and questions describing output or results. 

 

In all cases I attempted to interview the person who was primarily responsible for staffing the DRB in the respondent community.  In most (8) cases I spoke with the Zoning Administrator.  In one case I spoke with a Development Review Coordinator, and in another I spoke with a Planning Assistant who was assigned to staffing the DRB.  What follows is a summary of the responses to the list of questions.

 

Background Questions:

 

·        Eight of the ten communities have had a DRB for at least five years.  The other two are new DRB users, having had such a structure for 1.5 and 2 years, respectively.  All told, the average was 5.1 years.  The longest running DRB has been operating for eight years.

 

·        In nine of the ten communities, the initial DRBs included members of the former Zoning Boards of Adjustment.  In the tenth community the staff person was not there at the time and did not know.

 

·        In six of the ten communities the initial DRBs included members of the Planning Commissions.  Again, the information was not available in one community.

 

·        On only three of the ten DRBs are there currently members who also sit on their Planning Commissions.  However, several respondents reported that there were Planning Commission members appointed as alternate members of their DRBs.

 

·        The average size of the DRBs was 6.6 members, with size ranging from five to nine.  The most common size was seven members, reported by six of the ten communities.

 

·        Six towns reported that they had alternate members, ranging in number from two to five.  The average number of alternate members was three.

 

·        DRBs generally meet twice a month, although two communities reported that their DRBs  meet only once a month.  In all cases it was noted that if there were no projects to review, meetings would be skipped.  A couple of communities stated that they would hold special meetings if necessary to keep a project moving along.

 

·        Given the range of community sizes, it is not surprising that there is considerable variation in the number of cases considered at a typical meeting.  The range was 1.5 to eight cases, with the average being 4.6.

 

·        There was a similar variation in reported meeting length, ranging from two hours to over six hours.  The average was three hours.

 

·        The DRB meetings are tape recorded in nine of ten of the communities.  Similarly, nine of the ten communities report that the official minutes of the meetings are summaries of key points and motions.   The tapes are generally used to assist in creating the written minutes.  Only one community reported that the minutes were verbatim transcriptions of the tape recordings.


 

Staffing Questions:

 

·        In general, the Town’s Zoning Administrators staffed their DRBs.  Two of the smaller towns used a part time clerk to staff the Board but noted that the Zoning Administrator (ZA) meets with applicants but does not attend DRB meetings.  In the larger towns multiple persons were identified as staff to the DRB, including the ZA, the Town Planner, and sometimes a Planning Assistant or a Development Review Coordinator.

 

·        Two towns reported that their primary DRB staff person worked only twelve hours per week.  One reported thirty hours per week.  The remaining seven reported full time DRB staff persons.

 

·        The ZA typically had other responsibilities, generally the administration of all zoning matters such as permits, fees, enforcement, etc.  In four cases the ZA is also the Town Planner and is responsible for staffing the Planning Commission and doing long range planning work.  In the larger communities where multiple staff was assigned to DRB work, the staff works together closely, usually under the direction of the Town Planner or the Zoning Administrator. 

 

·        In all cases, staff prepared agendas for the DRB meetings.

 

·        Except for the town that uses a DRB Clerk, DRB staff reported that it regularly met with applicants prior to DRB meetings.  In the town with the clerk, it was reported that the ZA met with applicants.

 

·        In seven of the ten towns, staff reported that they did detailed reviews of proposed developments prior to DRB review.

 

·        In six of the ten towns, staff reported that it prepared detailed, written staff reports on proposed developments prior to DRB review.

 

·        In the six towns where staff prepared written reports, staff also prepared suggested conditions for approval.

 

·        In nine of the ten towns, staff prepares the final decision. The exception is a town in which the minutes of the meeting constitute the written decision.  In this case the Board crafts the motion of decision, including any conditions, and votes on the motion.  When the chair signs the minutes after approval at the next meeting, the decision becomes official.

 

·        In five of the ten towns staff reported actually taking minutes.  This may reflect a misunderstanding of the questions.  If there was someone other than board members taking minutes, it was interpreted as staff in some cases while in other cases if the town retained a recording secretary it was not interpreted as staff.

 

·        In all cases, staff attends all DRB meetings.  Where there is multiple staff, all attend the meetings.

 

·        In seven of the ten towns, staff reported doing a review of applications early enough to allow deficiencies to be identified and corrected prior to the DRB review.  In some cases this was a cursory review only to determine completeness (see next question).  Two of the seven report that they do an early review only if they have time.

 

·        In seven of the ten communities staff reported that they generally determine that applications are complete before scheduling them for DRB review.  In one case this was done only for larger applications.  In the smaller communities, no such determination was made prior to DRB review.

 

·        Of the six towns where staff reported that they prepare detailed written reports,  staff in five communities reported that the reports were distributed to Board members and applicants prior to the DRB meeting.  In most cases this means that the reports were distributed during the second half of the week prior to the meeting. One town reported sending the reports to applicants two weeks before the meeting.  In one town the staff reported that the reports are distributed at the meeting.  In all cases, reports are distributed to others only if specifically requested.

 

·        Of the six towns where staff reported that they prepare detailed written reports, staff in five cases indicate that the reports contain suggested conditions for approval.  One staff person noted that suggested conditions were not part of the reports, but were distributed to the Board during the discussion.

 

 

Procedure Questions:

 

·        None of the ten communities have adopted the Municipal Administrative Procedures Act (MAPA) to guide DRB operations.

 

·        In none of the ten communities do DRBs conduct “on the record” reviews.

 

·        Eight of the ten communities report that witnesses are sworn in before they offer testimony at meetings.  In general this is a group swearing at the beginning of a meeting where everyone who thinks they may speak are asked to rise and take the oath.  In one of the two community where witnesses are not sworn, the staff feels that the Board should revise its procedures to include that practice.

 

·        In all ten cases the staff reported that their DRB follows Robert’s Rules of Order or some similar format, which may be referenced in the Board’s adopted rules of procedure.

 

·        In one of the ten communities staff reported that the DRB required people to sign up in advance if they wished to testify at a meeting. 

 

·        In eight of the ten communities the Board allows virtually anyone attending the meeting to speak if they wish.  In two communities there was an attempt to limit participation  to abutters or “interested parties” as defined in the statute.

 

·        In all cases, notice of the meeting was sent to all abutters.  However, staff reports were only distributed if specifically requested in advance.

 

·        On a subjective level, most DRB staff who distribute reports feel that most DRB members read them prior to the meeting.  In one case the reports are distributed at the meeting, in part because staff felt that the volunteer members will not have time to read them in advance.

 

·        In general, DRBs do not do site visits except for complex developments or where there is the possibility of significant visual impacts, or where there is difficult topography.  The determination is often made at the DRB meeting and scheduled for a future meeting.  In some cases individual board members visit the sites prior to meetings.

 

·        In all ten cases staff reported that they participate in open meetings and hearings.  In only nine cases did staff report participating in deliberative sessions.  When asked to describe their participation, all stated that their role was to answer questions about the staff reports and/or the regulations.  When asked if they questioned applicants or other witnesses they generally said no, although one said on rare occasions if something pertinent to the regulations needed to be brought out.  When asked if they participated in DRB discussions about applications, all said no.  One staff person offered the opinion that the ZA was essentially a party to the review, just like the applicant, and should not participate in closed deliberations.  In all cases, when the matter under review was an appeal of a decision by the ZA, the ZA’s role in the discussions was very limited and formal.

 

·        In eight of the ten communities staff reported that their DRBs always used deliberative sessions (some stated that this might be omitted for decisions that are extremely simple and straightforward.  In the other two communities it was reported that the board frequently uses deliberative sessions, but not always.

 

·        When asked if the DRB ever found applications to be incomplete after the formal review was underway, staff in four towns said that it rarely occurred, staff in four towns said that it occurred sometimes, and staff in two towns said that it never occurred.  When an application was found to be incomplete, the Board generally recessed the review to a future meeting.  One staff members said that occasionally a  board member would vote to deny an incomplete application.

 

·        In nine of the ten communities it was reported that the DRBs generally issue decisions with formal findings and conclusions and conditions of approval.  The exception was the town in which the decision was in the minutes.  Even in that community, decisions on appeals of actions by the ZA were more formal with findings and conclusions.  The ZA in that town felt that it would probably be good if the DRB began issuing formal decisions in all cases.

 

·        In eight of the ten communities (including the town where the decision is in the minutes), the DRBs craft their decisions (usually in closed session) and then immediately vote on them in open session.  Staff then drafts the written decision based on the discussion and the motion.  This is circulated to at least the board chair for correction and then signature by the chair.  It becomes official upon being signed.  In the other two communities the decision is drafted by staff and voted on at the next meeting.

 

Output and Results Questions:

 

·        Staff, at least, appear to be happy with the functioning of their DRBs.  All reported that they felt that they had a good procedure that worked well and eliminated some duplicate meetings.  The one negative was a comment that the Board occasionally overstepped its authority.

 

·        When asked of they had any sense of how applicants felt about their DRBs, most staff reported that they had not heard anything and assumed that applicants were satisfied, or that they had heard nothing but positive comments.  The exceptions include a report that applicants felt that the Board occasionally overstepped its authority, and a reported concern with the use of closed deliberations.

 

·        Nine of the ten staff persons reported that they felt that the Board’s decisions were expeditious.

 

·        When asked how many DRB meetings it would take for a typical site plan approval, the range of answers was from one to three meetings, with an average of 1.4.

 

·        When asked how many DRB meetings it would take to obtain sketch or concept approval for a subdivision, the answers ranged from one to two meetings with an average of 1.2.  Note that one of the ten communities does not have subdivision regulations.

 

·        When asked how many DRB meetings would be required t obtain preliminary subdivision approval, the answers ranged from one to two meetings with an average of 1.3.  Again, note that one of the ten communities does not have subdivision regulations.

 

·        When asked how many months it would take for a typical minor subdivision (2-3 lots) to go completely through the process, the answers ranged from one to fifteen months, with an average of 2.6 months.  In the town reporting fifteen months, it must be noted that the approval process for residential developments includes obtaining a preliminary phasing allocation which can only be obtained once a year.  In all cases it was noted that the total time depended on how quickly the applicant turns around material for the next steps in the process.

 

·        When asked how many months it would take for a typical major subdivision (8 + lots) to go completely through the process, the answers ranged from three to eighteen months, with an average of 6.3 months.  Again, note that the town reporting the longest time has an extra step in the approval process for residential developments, as noted above.  Again, the total time depended on how quickly the applicant turns around material for the next steps in the process.

 

·        When asked how far into the future they are scheduling DRB meetings, two towns reported that they were scheduling at the next meeting (approximately two weeks) but the average lead time was 1.5 months.

 

More details on the above findings are presented in the following table.

 

Number of Meetings For:

 

 

 

 

 

mean

median

mode

Site Plan

1

1

1.5

1

1

1.5

3

2

1

1

 

1.4

1

1

Sketch

1

1

1

1

1

1.5

2

1

--

1

 

1.2

1

1

Prelim

1

1.5

1.5

1

1.5

--

2

1

--

1

 

1.5

1.25

1

Number of Months For:

 

 

 

 

 

 

 

 

Minor

6

1

2

5

15

--

3

2

--

2

 

2.6

2.5

2

Major

10.5

12

12

9

18

--

6

3

--

3.5

 

6.25

9.75

12

Lead Time for Agendas (months)

 

 

 

 

 

 

 

3

1.5

2

1.5

2

0.5

2

1

1

0.5

 

1.5

1.5

1.5-2.0

 

 

·        When asked if they could suggest any improvements to their DRB operations, seven of the ten respondents offered suggestions.  These are summarized below:

 

·        More training for DRB members, particularly on how to reduce the amount of repetitive comments at hearings (mentioned tree times)

·        Amend the Ordinance to include a waiver to set backs or change the variance criteria (mentioned once)

·        The Board should follow the bylaws more closely (mentioned once)

·        Speed up turnaround time for decisions (mentioned once)

·        Make sure that applications include all information required by Board (mentioned once)

·        Better quality applications (mentioned once)

·        DRB should issue formal decisions, swear witnesses, and reconsider use of closed deliberative sessions (mentioned once)

Possible Applications of findings to

Hinesburg’s Development Review Board

 

The Town of Hinesburg created its Development Review Board approximately two years ago[1].  The Board contains nine members and meets twice per month.  There are typically four items on an agenda and meetings reportedly last approximately four hours.  Meetings are not tape-recorded but minutes provide a summary of key statements and actions.  Recently the Board has started using closed deliberative sessions.  The DRB is currently served by three staff members, each of which devote a portion of their time to DRB matters.  Staff currently prepares technical staff reports but does not provide suggested conditions for approval.  Packets are distributed to the Board and applicants on the Thursday prior to Tuesday meetings.  The DRB does not do “On The Record” reviews and does not swear in witnesses.  Meetings are informally run.  Deliberations tend to lead to consensus which is the basis on which staff prepares a draft written decision.  The decision is acted upon at a subsequent meeting.  The typical times for approvals appear to be slightly longer than the averages reported by the ten communities surveyed.

 

Beginning in the summer of 2004 the Town has been reviewing the DRB and looking for ways in which it might be improved.  This study is a part of that review.

 

As a starting point it is noted that the Development Review Board serves the Town as a whole by carrying out the development review activities spelled out in the Zoning Ordinance and Subdivision Regulations.  Consistent with Vermont’s Planning Law, these include Site Plan Approval, Subdivision Approval, Conditional Use Approval, hearings on requests for Variances, and hearings on appeals of decision by the Zoning Administrator.  The Board is to literally enforce the provisions of the ordinance and regulations.  Ideally, the Ordinance and Regulations are sufficiently clear that there are few instances where the DRB makes discretionary decisions.  Development Review decisions should be based on whether or not the application satisfies the requirements of the Ordinance and/ or Regulations, and whether or not there are specific conditions which, if implemented, will cause the application to satisfy the requirements of the Ordinance and/or Regulations.

 

The question becomes how to allow the Board to do its work efficiently and expeditiously.  There are three sets of factors or issues that can facilitate the Board’s work;  a) staffing issues; b) meeting process issues; and c) the availability of adequate information.  Comments regarding the first two sets are based largely on the survey results, supplemented by my experience.  Comments regarding the third set are based almost entirely on my experience.

 

Staffing Concerns:

 

In Hinesburg the Planning and Zoning (Department) is made up of three positions, two of which are full time.  All three positions provide staffing to the DRB. Based on the staff hours analysis conducted during the fall of 2004, it would appear that the sum total of the time devoted to DRB work from all three positions is approximately one full time equivalent position.  It is not clear that there is any one person responsible for ensuring timely and consistent support to the DRB.  The Administrative Assistant does the initial reviews of applications for completeness.  The Zoning Administrator and the Town Planner divide the applications between them, each  taking their assigned cases from technical reviews through to drafting the final decisions for Board action.

 

For purposes of analysis it is useful to distinguish between clerical staff support and technical staff support.  Clerical staff support includes taking and preparing minutes of meetings, preparing agendas of meetings, ensuring that copies of decisions and agendas are properly filed, and the administrative aspects of processing applications to be heard by the Board.  Technical staff support includes meeting with applicants, reviewing applications, preparing staff reports (if used), preparing suggested conditions of approval (if used), and advising the Board and applicants regarding the requirements of the Ordinance and Regulations.

 

Clerical support can easily be provided by someone other than the technical support staff.  Minutes are often taken by outside recording secretaries.  Agendas can be prepared based on communication with the technical support staff.   It is important that an application not be placed on a DRB agenda until staff has determined that the application is complete.

 

Technical support to the DRB must be timely, rigorous and consistent.  Where technical support is shared between two or more individuals, there should be one person designated as responsible for timeliness and content of the work.  The actual work may be delegated but that one person must ensure that projects are properly reviewed, the requirements of the Ordinance and/or Regulations are made clear, and that all information is clearly presented to the Board.  In order to do this it is important that this designated person attend the Board’s meeting. 

 

What follows is a list of technical support tasks, which will facilitate the DRB in its reviews and deliberations.  It is understood that the staff person cannot speak for the Board and cannot make any commitments.  The staff person puts forth the Town’s requirements as set forth in the Ordinance and/or Regulations.

 

·        An informal discussion with applicants prior to submission of an actual application.  At this point the staff person can raise any red flags regarding compliance at an early stage so they can be addressed prior to significant project design expenditures.  Staff can also brief applicants on how to expect the approval process to unfold.

·        Once an application is received, staff should conduct an initial review to ensure that all required application materials are included.  This determination should be based on a comprehensive check list for the type of approval being sought.  There should be a place on the application form or folder to note the date on which the application is considered complete.  A project should not be placed on a DRB agenda until it is complete.

·        A detailed technical review of the project, based on all of the requirements set forth in the Ordinance and/or Regulations should be completed, using all of the information provided in the application plus staff’s knowledge of the site and area.  This technical review should be recorded in a technical staff report.  This should systematically go through all requirements, noting those that appear to be met and those that are problematic.  Staff may develop a shell or template document to facilitate this review.  The report should note areas where staff believes that no conclusions can be reached, either because the information provided in the application is insufficient or because the regulations are unclear.   The staff report should be distributed to the applicant (and representatives) and to the Board.

·        If staff believes that the proposed development can be made to comply with the Town’s Ordinance and/or Regulations only if certain conditions are satisfied, staff should include in the report suggested conditions to approval.  If staff believes that the proposed development is so far from what the ordinance/ and/or Regulations requires that there is no reasonable way to bring it into compliance, staff should recommend that the application be denied.

·        Staff should be available at the DRB meeting to explain to the Board the basis for the technical review and suggested conditions, and should be prepared to answer questions at the Board meeting.  Once the information has been conveyed to the Board, staff should not debate the matter.  It is the Board’s prerogative to accept, modify and accept, or reject staff recommendations.

·        At DRB meetings staff must maintain a position of neutral objectivity (It matters not whether staff “likes” an application, only whether the application satisfies the requirements of the Ordinance and/or Regulations.)  It is not appropriate for staff to enter into the Board’s debate on the merits of the application.  It is appropriate for staff, when asked, to answer questions related to the regulations and perhaps to help with language for conditions.

 

As noted above, it is important that there be one staff person designated as responsible for seeing that all of the technical support activities are completed in a timely manner and consistently represent the requirements in the regulations.

 

Meeting Process Concerns:

 

Meeting process concerns relate to activities that keep meetings moving in a productive and time efficient manner.  Addressing these concerns is, to a large extent, up to the Board Chair.   It must always be remembered that the purpose of the Board is to effectively ensure that proposed development complies with the Town’s written and adopted regulations (Zoning Ordinance and Subdivision Regulations).  What follows are some suggestion on how meetings can be effective and efficient.  A more detailed version of these suggestions is contained in the appendix.

 

·        The meeting should observe some format such as Robert’s Rules in order to maintain orderliness and civility.

·        People should speak only after being recognized by the chair.

·        All witnesses should be sworn before they present testimony

·        Staff reports should be made part of the minutes.

·        The Board should hear the application in the following sequence:

1.      General presentation of the proposed development by the applicant.

2.      Applicant’s response to issues raised in the staff report (not proposed conditions at this point)

3.      Applicant’s comments on the suggested conditions. 

4.      Questions by Board members

5.      Audience comments on the application.

6.      Closing of hearing or discussion.  (Note:  The hearing may be recessed to preserve the option of re-opening it to obtain additional specific information.)

·        Deliberations:  On the basis of information gathered during the hearing or open session (including the staff report and all representation made by the applicant and other sworn witnesses) the Board considers whether the application complies with all requirements of the Town’s Ordinance and/or Regulations.  Deliberations may be open or closed, but if open the applicant must not participate unless asked a specific question by the Board.  The deliberations should lead to one of three conclusions:

1.      If the application, as submitted, does satisfy all requirements, a decision to approve the application can be crafted.

2.      If there are requirements that are not satisfied, can conditions be applied that will bring the application into compliance?  If so, a decision to approve with those  conditions can be crafted.

3.      If the application does not comply with all requirements, and if there are no reasonable conditions that will bring it into compliance, a decision to deny the application should be crafted.

·        Action:  If the Board has been in closed deliberative session it should return to the open meeting.  A motion should be made and acted upon, which incorporates the decision crafted during deliberations.  

·        Written decision:  Based on the motion, staff can prepare a formal written decision for signature by the chair.  This may be distributed in draft form to board members prior to being signed.

 

The above steps outline a general set of procedures that the Board can follow to keep its reviews and decisions expeditious.  Whatever process the board uses, it is important that applicants have realistic expectations about how the Board’s reviews and deliberations will take place.  The procedures may be memorialized in the Board’s adopted operating rules of procedure.  Perhaps more important, a description of the process should be conveyed to every applicant, perhaps as a part of an application package. Also, whenever staff meets with applicants, the process should be described, unless the applicant is already familiar with it.

 

Information Concerns:

 

The Board’s review and decision on any application is based on whether or not the application complies with the requirements set forth in the Zoning Ordinance and/or Subdivision Regulations.   To make such a determination the board must have adequate information.  Information about the proposed development is provided by the applicant in the application package.  The quality of the information provided in the application will have a significant impact on the time required for the application to wend its way through the process to a decision.  Information regarding the Town’s Regulations is provided by staff.

 

A:  Information About the Proposed Development:  The starting point for ensuring adequate information is the list of application materials included in the Zoning Ordinance and Subdivision Regulations.  This should include specification of the minimum items of information for each type of application.  In addition, any information typically needed for the Board to determine compliance with specific requirements of the Ordinance and Regulations should be listed.  Together these make up a checklist for each type of application.  The checklist should be a part of an application package given to any prospective applicant before an application is submitted. 

 

The Zoning Ordinance and/or Subdivision Regulations should specify under what conditions engineering drawings and/or certification will be required for improvements such as streets and roads, driveways, connections to public water and sewer systems, on-site waste water treatment systems, stormwater treatment systems, etc.  These requirements should be reflected in the checklist.

 

An initial review by staff should determine whether or not all items on the checklist have been provided. Note that satisfying the checklist does not imply that an affirmative decision will be made, only that the necessary information for a decision has been provided.  Only after the application has been deemed complete should it be scheduled for Board review.

 

B:  Information regarding the Town’s Regulations:  Assuming that the applicant has provided the necessary information describing the project, staff must merge it with technical information describing the Town’s requirements as set forth in the regulations.  In the ideal world the staff report will individually address each requirement and present staff's judgement as to whether the requirement is met or not.   If a requirement is not met, staff should suggest one or more conditions that would bring the application into compliance.  This rigorous format provides a sound information base for both the discussions at the hearing or open session and the Board’s deliberations.

 

  It is critically important that staff be impartial and objective in conducting this review and drafting the staff report.  Whether or not staff likes the proposed development is irrelevant. The only question is whether the proposed development complies with all of the Town’s requirements, or can be made compliant by the imposition of a set of clear conditions.

 

This information, perhaps supplemented by information gathered at the hearing, will serve as the basis for the Board’s decisions.   Having the information complete and presented in a carefully organized manner can significantly reduce the time required for the DRB review, both at the hearing and during deliberations.

 

The preceding pages present a somewhat idealized model of DRB operations.  There is no question that many of the individual elements of this model already exist in Hinesburg.  It is hoped that the Town will adapt the ideal model in ways that will further facilitate the DRB’s efforts.


 

 

 

APPENDIX

 

 

 

1.                 List of questions used to guide the interviews

 

2.                 Detailed discussion of meeting process concerns.

 

 


DRB SURVEY QUESTIONS

Name of Town ________________________

Interviewee_____________________      Date of Interview_________

 

Background Questions:  

1.      How long has your town used a Development Review Board (DRB)? ______

 

2.      When the DRB was first formed, did the membership include members of the former Zoning Board? _____, or Planning Commission? ______

 

3.      Are there currently any Planning Commission members on the DRB? ______

 

4.      How many members does the DRB have? ______

 

5.      How often does the DRB meet? ______

 

6.      How many cases are on a typical DRB agenda? ______

 

7.      How long does a typical DRB meeting last? ______

 

8.      Are DRB Meetings recorded? ______

 

9.      Are minutes verbatim or do they include only important items to capture the gist of the discussion? ________________________________________________________

_____________________________________________________________________

 

Staffing Questions:

1.      Who provides staff support to the DRB?  Zoning Administrator? ___, Other? ____

 

2.      Is there a single staff person who serves the DRB? ______

 

3.      Is the staff person full time or part time? _____   If PT, how many hrs per week ____

 

4.      Does the staff person have other responsibilities?  What are they? ________________

 

 

5.      What does staff do for the DRB?

·        Prepare agendas? ______

·        Meet with Applicants? ______

·        Determine whether applications are complete? ______

·        Conduct Project Reviews? ______

·        Prepare detailed staff reviews of applications? ______

·        Prepare recommended decision and conditions? ______

·        Draft final decisions? ______

·        Take minutes of Meetings? ______

·        Participate in DRB discussions? ______

·        Other (describe __________________________________________________

 

6.      Does the staff person attend all DRB meetings? ______

 

7.      Does staff do an initial review of applications early enough to allow deficiencies to be identified and corrected before formal staff reports are prepared? ________

 

8.      Does staff determine that applications are complete before scheduling a review by the DRB? _________

 

9.      Are staff reports distributed to applicants in time to allow improvements prior to the DRB meeting? ________________________________________________________

 

10.  Are staff reports distributed to Board members in time to allow them to be read prior to the DRB meeting? ___________________________________________________

 

11.  If staff reports are prepared, do they include suggested conditions for approval? ____

 

Procedural Questions:

1.      Has the Town adopted the Municipal Administrative Procedures Act to guide the DRB? _____

 

2.      Does the DRB do “On the record” reviews _____

 

3.      Does the DRB swear in witnesses who give testimony? ______

 

4.      Does the DRB follow any format such as Robert’s Rules of Order? ______

 

5.      Does the DRB require people to sign up in advance of they wish to testify at a meeting? ______

 

6.      Is anyone allowed to speak at meetings or only abutters of applications being heard? _____________________________________________________________________

 

7.      Does the DRB send notice to all abutters of pending applications? _______________

 

8.      Are staff reports distributed prior to meetings?  To DRB members? ____, To Applicants? ____, To others? ______

 

9.      Does the DRB send copies of staff reports to all abutters prior to meetings? ______

 

10.  Do DRB members typically read staff reports prior to the meetings? ____________

 

11.  Does the DRB do site visits?  Always? ___, On Complex applications only? ____. Rarely? _____, Never? _____

 

12.  What is the role of the staff person at DRB meetings?  Observe only? _____, Present staff report and answer questions of fact? _____, Participates in discussion, questions applicants, just like Board members? _____, Other? _____

 

13.  Does the DRB use closed deliberative sessions?   No? ____, Occasionally? ____, Frequently? ____, Always? ____

 

14.  How often does the DRB determine that an application being reviewed is not complete? _____  What happens in such cases? ______________________________

_____________________________________________________________________

 

15.  Does the DRB issue formal decisions containing Findings and Conclusions? ______

 

16.  If not, what form do DRB decisions take? ___________________________________

 

 

17.  Does the Board craft its decisions at meetings? ____, or agree on items to be included and let staff draft decisions for vote at a future meeting? ____ or other? ___________

_____________________________________________________________________

 

Results Questions:

1.      Are you happy with the way your DRB functions? _____  Why? ________________

 

 

2.      How have applicants reacted to the DRB? ______________  Are they satisfied? ____  Why or why not? ______________________________________________________

 

3.      Are applications reviewed and decisions reached expeditiously? ________

 

4.      How many DRB meetings are required for a typical Site Plan Approval? ______

 

5.      How many meetings are required for a typical sketch or concept approval of a proposed subdivision? ______

 

6.      How many meetings are required for a typical Preliminary Subdivision approval? ___

 

7.      How long does it typically take for a small (2-3 lots) subdivision to get completely through the process? ______

 

8.      How long does it typically take for a large (8 + lots) subdivision to get completely through the process? ______

 

9.      How far into the future are projects scheduled for DRB review? ______

 

10.  What do you think could be improved? _____________________________________

DETAILED DISCUSSION OF MEETING PROCEDURES

 

Meeting Process Concerns:

 

Meeting process concerns relate to activities that keep meetings moving in a productive and time efficient manner.  Addressing these concerns is, to a large extent, up to the Board Chair.   It must always be remembered that the purpose of the Board is to effectively ensure that proposed development complies with the Town’s written and adopted regulations (Zoning Ordinance and Subdivision Regulations).  What follows are some suggestion on how meetings can be effective and efficient. 

 

·        The meeting should observe some format such as Robert’s Rules in order to maintain orderliness and civility.  This can be referenced in the Board’s operating rules and procedures.  Having such a format can greatly assist the chair in keeping the meetings moving forward.

·        People should speak only after being recognized by the chair.

·        All witnesses should be sworn before they present testimony.  This can be done at the beginning of the meeting by asking everyone present who thinks they might wish to speak to stand and repeat the oath.  Later in the meeting witnesses can be asked to verify that they have taken the oath.  If not they can be sworn before they testify. This is an important factor, particularly for applicants and their representatives.  Every statement made by the applicant about his/her proposed development is evidence used by the Board to determine whether or not the development complies with the Town’s regulations.  It must be truthful.  In a sense, these representations become conditions of approval. 

·        Staff reports should be made part of the minutes.  When an application is opened for consideration at the meeting the Chair should confirm that the applicant has seen the staff report and ask if the applicant will waive formal reading of the report and allow it to be entered into the minutes.  The alternative is to literally read the entire staff report, word by word, into the minutes.  I have never heard of this request for waiver being refused. 

·        The chair should then ask the applicant to present the proposal according to the following outline. (These are not intended to be taken literally, but to describe a process and sequence of events):

1.      The chair should then ask the applicant to make a general presentation of the proposed development.

2.      The chair will ask the applicant if he/she has any response to issues raised in the staff report (not proposed conditions at this point).  These issues should be discussed in order.

3.      When all aspects of the proposed development have been discussed, the chair may then ask the applicant if they have any comments on the suggested conditions.  It is important to note that even though an applicant may not like a condition, it may be necessary to bring the application into compliance with the Town’s regulations.

4.      At this point the chair may invite members of the audience to comment on the application.  (Note, most towns allow anyone who comes to the meeting to speak, but technically it may be limited to abutters and interested parties).  The chair should request that speakers identify themselves, and that they refrain from repeating points already made by others.  The chair should discourage Board members from entering into debate with members of the audience. The intent is to gather information.  In response to comments from the audience the chair may ask if the applicant wishes to comment.  Without effective leadership from the chair this process can become lengthy and acrimonious.

5.      The chair should ask members of the Board if they have any questions, either of the applicant or of staff.  If information is missing or incomplete, it can be identified at this time.  If necessary, the hearing or meeting may be recessed while additional information is provided.  It is often helpful to summarize what has been heard at this point.

6.      When the Board determines that all available information has been gathered, the hearing may be closed or the meeting may move on to other matters.  If the Board intends to deliberate in open session it may opt to do so at this time.  If the Board intends to deliberate in a closed session it makes sense to defer until all other cases to be deliberated have been heard.

·        Deliberations:  In deliberations the Board considers the basic question of whether the application complies with all requirements of the Town’s Ordinance and/or Regulations.  This determination must be made on the basis of evidence gathered in open session, including the staff report and all representation made by the applicant and other sworn witnesses. If the staff report states all requirements and identifies those with which the application does and does not comply, that report can be very useful in structuring the deliberations.  The Board can be asked if it agrees with the staff report, and if not, can focus on those items with which members disagree.  Note that the question is not whether or not the board individually or collectively likes the application, but whether it complies or can be made to comply with the regulations.  It is at this point that the suggested conditions can be considered.  Ultimately the deliberations should craft a decision to either approve or disapprove the application and include any conditions necessary to ensure compliance with all requirements.

·        At this point the Board can follow one of at least two procedures.  It can ask staff to draft a final motion for action at the next meeting, or it can go back into open session vote on a motion to approve, approve with conditions, or disapprove the application.  In this case it may then be wise to have staff draft a final decision carefully reflecting the motion, for signature by the Board chair.  The latter approach allows the matter to be concluded without appearing on the agenda of a later meeting.  Most of the towns surveyed follow this procedure.

 

The above steps outline a general set of procedures that the Board can follow to keep its reviews and decisions expeditious.  Whatever process the board uses, it is important that applicants have realistic expectations about how the Boards review and deliberations will take place.  The procedure may be memorialized in the Boards adopted operating rules of procedure.  Perhaps more important, a description of the process should be conveyed to every applicant, perhaps as a part of an application package. Also, whenever staff meets with applicants, the process should be described until such time as it is generally understood and accepted.



[1] Information on Hinesburg DRB operations was derived from an interview with the Zoning Administrator, a meeting with all Planning and Zoning staff, observation of a DRB meeting, and review of internal review and evaluation documents.