HINESBURG DEVELOPMENT REVIEW BOARD
MINUTES OF AUGUST 20, 2002
Approved 9/03/02
Present: Tom McGlenn, Howdy Russell, Wayne Burgess,
Ted Bloomhardt, Greg Waples, and Clint Emmons.
Member
Absent: Peter Ross.
Members of
the Audience: Beverly
Soychok, Howard & Inez French, Sandy Wynne, Laura Jackson, Robin and Larry
Winters, Lisa Moulton, Linda O’Brien, James & Nancy Stowe, Tim & Tom
Ayer, Sam Evanson, John MacEntee. Also Peter Erb, Zoning Administrator; Alex Weinhagen,
Town Planner; and Jeanne Wilson, Town Administrator.
1. MINUTES - Wayne
Burgess made the motion to accept the minutes of August 13, 2002 and this
motion was seconded by Clint Emmons and passed.
2. BARONE – FINAL PLAT AS A
PLANNED RESIDENTIAL DEVELOPMENT Tom
McGlenn opened the public hearing at 7:35 for review of a request for final plat
approval for Barone Construction Inc. for property currently owned by Ernest
& Theresa Giroux, represented by Russell
Barone. This appeal was also for a
conditional use permit as well as site plan approval as a Planned
Residential Development (PRD) and governed by Section 4.5 of the
Hinesburg Zoning Bylaw. This subdivision consists of 6 single-family
residential units, a second phase, not
applied for at this time, of 30 units of elderly housing and the remaining approximately
56 acres. There will
be 5 houses on a new private road to be named
Mulberry Lane and one house with a separate driveway cut onto the
Mechanicsville Road.
Russ
Barone then went through the requirements for submittal from the preliminary
plat approval for this project and granted on 6/04/02. The following items from those conditions
were then discussed:
·
The two
road-cuts onto the Mechanicsville Road, have been
approved by the Select Board.
·
Under the
PRD section they are requesting a waiver in the
setback for the garage on lot #1.
·
There has
been a blasting plan submitted
·
The deeds
will cover the building envelopes for the houses and accessory
structures. Any
accessory structure cannot be higher in
elevation than the house on each lot.
·
As Norway
maples are no longer accepted as street trees, he is willing to plant Lindens.
·
There will
also be a cluster of evergreens on the Mechanicsville Road rather than shade
trees due to the wetland on the corner.
·
A utility
location plan has been submitted.
·
The
requirements for final plat submittal had also all been met and Russ explained that his
engineer will certify each step of the construction of this roadway and supply
as-built plans.
There was
then a discussion of the sidewalks associated with this proposal, which
include a section on the east side of the Mechanicsville Road and on the south
side of this new Mulberry Lane. The
concern was as to what level of development would trigger construction of these
sidewalks and whether they would be asphalt or concrete. Russ agreed that they would be concrete when
eventually
constructed. Town Administrator, Jeanne Wilson had
submitted a memo concerning these sidewalks stating that the Select Board is “willing to be
flexible with the timeline for the sidewalk installation.”
There were
several neighbors in the audience and they brought up some of the following
concerns:
·
The house
on lot 6 seems to be quite close to the last house on Hawk Lane, but after
reviewing the plans, Russ explained that actually this lot is further west than
the Hawk Lane house.
·
There is a
lot of land in this parcel that is not being used for this subdivision and
therefore is it necessary to crowd the houses on these 1/3-acre lots? Russ explained that this is
to fit the pattern of development of a Village District.
HINESBURG
DRB
Minutes of 8/20/02 Page 2
of 5
·
The houses
on Hawk Lane will be greatly affected if future phase of this project connects
the Mechanicsville Road with the Lavigne Hill Road and Mulberry Lane becomes a through
street. The neighbors felt this would
create more noise and traffic and affect their quality of life. Sam Evanson, who lives off Lavigne Hill
Road, said there is another side to this issue in that it
would help the traffic situation on that road and
become a connection to the village area.
·
There was
a question of whether car lights from lot #6 would shine into the houses at the
end of Hawk Lane and Russ explained that the garage and hedgerow would prevent
this from happening.
·
The
blasting schedule and level were also questioned and Russ is willing to notify
the neighbors when this is going to occur. Russ then stated that he hopes to have these houses constructed
and sold within one year and therefore this project
will not be a major disruption to the neighborhood.
·
There is a
stream between these two properties and the neighbors were concerned about
flooding of their lots. Russ explained
that this new road and its culverts would actually pull some of this run-off
down Mulberry Lane.
The DRB members then questioned Russ about
protecting the trees on the common land and the bank on lot #5. There is language in the covenants that
addresses these trees and Peter Erb had suggested language to cover this bank
and backyard on lot #5.
Tom McGlenn then made the motion to
close the public hearing and this motion was seconded by
Greg Waples and passed. Tom went through and the
members discussed some draft conditions of approval. It was decided that the staff should work on
which parts of the Protective Covenants should
be included in these conditions of approval.
These would include the maintenance and repair of
the common land. Jeanne
Wilson explained that once the Mechanicsville Road sidewalk is constructed the
Town would take it over and also maintain it.
Tom
McGlenn then made the motion to grant final plat subdivision
approval
to Ernest and Theresa Giroux as presented and conditioned
upon approval of these final plat conditions at the
next DRB meeting. This approval includes approval for this project as
a Planned Residential Development and also grants
site plan approval. (See
attached sheets)
BARONE –
DRAFT CONDITIONS OF APPROVAL
The Hinesburg Development Review Board hereby
grants final plat approval and approval for development on a private right of
way to Ernest and Theresa Giroux (Barone Construction Inc.) for a six-lot
single family Planned Residential Development on a 65 acre parcel of land owned
by Ernest and Theresa Giroux located off of Mechanicsville Road, as well as
Conditional Use Approval for moving the village – RR boundary per section 1.3
of the Hinesburg Zoning Bylaws The subdivision shall be as shown on Plans #1-6
by O=Leary-Burke
and a AProperty
Plat 7-lot Subdivision@ by George
Bedard, dated April 16, 2002.or as amended.
This
approval is subject to the following conditions:
1.Utility
lines shall be placed underground as required in Section 7.9.1 of the
Subdivision Regulations and depicted on
Sheet 2 of the Plat.
1.The lots
shall not be sold or a zoning permit issued for building construction until a
Subdivision Permit from the State Division of Wastewater Management is
obtained. or…This approval shall not be
in final until a Subdivision Permit from the State Division of Wastewater
Management is obtained.
1.All
exterior lighting shall installed or shielded in such a manner as to conceal
light sources and reflector/refractor areas from view from points beyond the
lot.
1.All structures shall be located within the
approptiate envelopes as depicted on the plat.
1.A roadway
serving more than one house is proposed.
The road shall be built in accordance with plans titled Barone, by
O’Leary-Burke, 5-1-02 or as amended, sheets 1 – 6 as applicable.
1.Before
obtaining a Certificate of Occupancy for the first dwelling on the shared road,
Mulberry Lane, the owner of the land shall require that the contractor or( engiIneer??) in charge
of road constructing construction
the road submit a
letter to the Zoning Administrator stating that the road has been built in
accordance with this approval and the standards specified in this condition
roadway
1.Town
approval of the two curbcuts shall be obtained from the Road Foreman prior to
the granting of the first CO.
1. The deed language set forth in the document titled
Declaration of Covenants, cConditions and rRestrictions of Mulberry Lane shall establish the
method of sharing the maintenance, repair, snow plowing and any other expenses
for the common portion of the roadway.
1.Before
obtaining a Certificate of Occupancy for the first dwelling, the owner of the
land shall obtain a letter from the power company and submit it to the Zoning
Administrator stating that the utilities have been installed in accordance with
the approved plans.
1."Substantial
Construction" for this subdivision shall consist of the construction of
the access road to the standards of the plans submitted for it. In accordance with Section 8.9 of the
subdivision regulations, if substantial construction has not begun within 3
years from the date of this approval, final plat approval shall expire.
1.In
accordance with State Statute, the mylar of this subdivision and a copy of the
conditions of approval shall be recorded in the Hinesburg Land Records within
90 days of this approval.
.
1.Any design
changes from the approved plat of the utility lines or sewage system shall be
approved by the DRB before installation. Minor changes in the position of the
utility or sewer system elements to avoid unforeseen problems shall not require
DRB approval as long as the “engineer” has been notified.
1.As- built
drawings of the sewage system, or the original drawings, certified by the
engineer to be the as built, shall be submitted to the Zoning Administrator
before the Certificate of Occupancy is issued for the last structure
constructed.
1.Each
individual lot owner shall be responsible to repair and avoid any future damage
caused by storm water to another lot or the shared portion of the road.
1.The owner
of Lot #3 shall be responsible for the maintenance and replacement of the cedar
trees indicated on the plat for screening.
1.All
blasting shall be done by a submitted document from Rochkaway Drilling and Blasting, entitled Blast Plan for
the Mechanicsville Rd.
1.The areas
exposed during construction shall be treated in a manner consistent with the
procedures contained in the Vermont Handbook for Soil Erosion and Sediment
Control on Construction Sites.
1.No further
subdivision of this property shall occur without review and approval of the
Hinesburg DRB
1.THE
MENTION OF ADDITIONAL UNITS IN THE COVENANTS and other submitted legal
language, does not indicate acceptance of the possibility of this
occurring until, and at such point as the necessary permitsd have been obtained
and any language included in the covenants etc. submitted with this application
have been reviewed to reflect the new application.
1.An iIrrevocable Offer of Dedication shall be reached
with the Town of Hinesburg for the road serving this subdivision and included
as part of this approval.
1.Street trees shall be planted no more than 40 feet apart on Mulberry lane,
on the north side except where it is planted with cedars, on the south side
beyond the hammerhead, and on mMechanicsville rRd. Such plantings shall meet the requirements of sSection 7.4 of the sSubdivision rRegulations and shall remain the responsibility of
the Mullberry Lane Homeowners association to maintain in good health or replace
within the next growing season with trees meeting the original requirements.
1.Sidewalks
on the road that serves the subdivision will not have to be constructed as part
of this phase of the development, however their construction and all costs may
be conditions of later permits granted to the residual lot. The road shall be
maintained in the winter to its full width to accommodate pedestrian
travel.
1.The
sidewalk on the Mechanicsville Rd. will be constructed in the proposed 20
sidewalk easement, before the final CO is issued unless agreement is reached
between the town and the owner of record of the subdivision that established
when and or if such sidewalk should be constructed. Such sidewalks shall be
concrete, 5’’ deep ( 6” deep across driveways) five feet wide on a
compacted layer of crushed gravel.
1.On the areas
designated as common lands, trees
greater than 4 inches in diameter at 1 foot above the ground shall not be
removed. However dead or diseased or other trees may be removed provided such
removal is necessary to sustain the health of the screening provided by the
forest. Sufficient trees shall be allowed to regenerate to preserve the
existing canopy.
1.Banks
shall either be at the angle of repose appropriate for the soils of the bank,
and also one that will support vegetation and resist erosion, as established by an engineer or other
qualified consultant or: if blasted ledge or a constructed wall over 6’
high, have screening consisting of conifer planted in front if they are visible
off lot.
1.
the height of these homes
No
structure on a lot shall be higher that the elevation of the primary structure
on that lot.
2. EAST WIND CONDOMINIUM ASSOCIATION –
CONDITIONAL USE & SITE PLAN
Lisa Murdock, representing East Wind
Condo Association and Jack Russell, was next
on the agenda to request site plan and conditional use approval to
construct carports and storage buildings at the East Wind Condominiums, located
on the west side of the Mechanicsville Road.
The review of this appeal had been continued at the July 9th
DRB
hearing in order for the applicant to present more information and to meet with
the tenants and other owners of these units. Twelve of these 16 unites are owned as rental
apartments by Jack Russell and the other 4 by individuals.
Lisa went
through the changes to the plans since the last meeting, which
include adding 3’ to the depth of the carports and
moving these slightly to stay out of the floodplain and adding 3 pole
lights at the carport locations. She also
presented a petition signed by the tenants and 3 of the 4 private owners
stating that they are in favor of building these carports and this project.
Lisa had submitted a new calculation
of lot coverage for this project, which involves both the
Village District and Rural Residential I, and she had
found that there would be an increase of 1.2 %. However, the facility has
pre-existing non-complying structures and therefore this issue would be
considered under the Conditional Use criteria.
The following issues were then
discussed with Lisa and the Board members and members of the audience:
·
There will be bollards at the
front of the playground for safety and some type of obstruction along the
drive between the buildings to keep vehicles
from parking there.
·
The
exterior lighting will be on all night for security and safety reasons.
HINESBURG
DRB Minutes of
8/20/02 Page 3
of 5
·
There will
be interior lighting of these carports and it was agreed that these should not
be visible outside the building. Lisa
Moulton, one of the unit owners, suggested that these lights be
motion sensor lights.
·
These
carports will be built to match the existing condo structures with bevelled siding
and asphalt roofing.
·
There will
be an enclosed storage area at the rear of each carport.
·
Each
section of the carports would be for two vehicles and there was discussion of
protecting cars if there is not a barrier between them.
·
These will
provide 24 parking spaces for the condos with 16 additional gravel spaces
directly in back of the two condo buildings.
Lisa
Moulton, as one of the individual unit owners, stated that she cannot support
this project and is concerned that she will be forced to buy this carport, which she
feels is inadequate. Greg explained
that this may be the
situation when someone owns a
condominium and is part of an
association.
Tom McGlenn made the motion to close
the public hearing and this motion was seconded by Greg Waples and passed. Tom McGlenn then made the following motion:
The Hinesburg Development Review Board hereby
grants site plan approval to Jack Russell, representing the East Wind Condo
Association, for construction of two carport units, storage
units, dumpster enclosure and relocating the playground. The
project shall be constructed as shown on the plat
titled “East Wind Condos, Site Plan” and dated
January 17, 2002 and last revised 7/26/02 and the plans
titled “East Wind Condominiums, Carport,
Storage Unit and Dumpster Enclosure” and dated June 20,2002; with the
following conditions:
1. Parking
shall only be in the carports or gravel parking areas in back of
the condominium buildings. If experience
indicates inadequate parking or unsafe traffic flow, the applicant shall
immediately present proposed modifications of the site plan to the Hinesburg
Development Review Board, and obtain approval of it.
2. All
exterior lighting shall be installed or shielded in such a manner as to
conceal light sources and reflector/refractor areas from view from points
beyond the lot. The three Gardco
Form Ten pole lights as specified on the site plan shall be installed where
indicated. The existing lights on the
rear of the buildings shall be removed.
3. Snow shall
be plowed to both sides of the gravel areas, away from the playground and
carports.
4. Construction
shall take place Monday through Saturday
commencing at 7:00 A.M. and ceasing at 5:00 P.M.
5. Colors of
the structures shall be chosen to blend with the surroundings.
6. The areas
exposed during construction shall be treated in a manner consistent with the
procedures contained in the Vermont
Handbook for Soil Erosion and Sediment Control on Construction Sites.
7. Any plants
and trees shown on the landscaping plan shall be properly maintained and any
plants or trees that die shall be promptly replaced. Two shade trees of 2” diameter shall be
planted so that they shade the playground.
8. The
applicant shall obtain a zoning permit from the Zoning Administrator
prior to construction.
9. The
parking spaces within the carports shall be separated with a barrier so that
the doors of neighboring cars cannot impact the other.
10. There
shall be no storage of hazardous materials in the carports or storage
buildings.
11. This
approval will expire within one year of this approval date. If a zoning permit has been obtained within
that year this approval will expire when the zoning permit expires, if
construction has not occurred.
12. Headers
shall be installed to delineate the gravel parking spaces on the east side of
the parking lot.
13. Storage
areas within the carports shall be enclosed cabinets at the rear
of the buildings. All storage within
the carports shall be within the enclosed cabinets and the parking space shall
be available for registered vehicles.
HINESBURG
DRB
Minutes of 8/20/02 Page 4 of 5
14. Lights interior to the units shall be on motion
sensors such that they turn off when people are not present. The lights shall shine towards the interior of
the carport units.
15. Staked concrete
curb stop shall be installed at the edge of the driveway starting 12 feet prior to the
south side of the condo units and continue to the parking area defined on
the plan. The remaining area shall be
seeded and maintained as grass lawn.
16. The water
line connection to the Town of Hinesburg water system shall be installed per
the submitted plan.
This
motion was seconded by Tom McGlenn and passed unanimously.
The second portion of this appeal
was for a conditional use permit for construction within a Flood Hazard Area as
governed by Article VI of the Zoning Bylaw.
The applicants had submitted letters from Karl Jurentkuff,
a State Floodplain
Management Engineer and April Moulaert, a
State Wetlands Ecologist. The submitted
plans meet the criteria of these two State letters. Clint Emmons questioned how much fill they
will be adding to meet Jurentkuff’s requirement and
Lisa explained they actually have to bring in very little.
Tom McGlenn then made the following
motion concerning the flood plain:
The
Hinesburg Development Review hereby grants conditional use approval to Jack
Russell, representing the East Wind Condo Association, for
construction two carport units in a Flood Hazard Area. The project shall be
constructed as shown on the plat titled “East Wind
Condos, Site Plan” and dated January 17, 2002 and last
revised 7/26/02 and on plans titled “East Wind
Condominiums; Carport, Storage Unit and Dumpster Enclosure” and dated
June 20,2002; and shall be subject to the following conditions:
1. The
floor level of the units shall be at least seven feet above the base flood
level as indicated on the plat, thus keeping all construction above the flood
plain as identified by Karl Jurentkuff, Floodplain Management Engineer for the State of
Vermont Water Quality Division.
2. A
letter shall be submitted from a
registered professional engineer certifies that there will be no increase in
flood levels during the occurrence of the base flood.
3. Any
construction shall be completed as shown on the plat and plan.
4. All
banks created by this construction shall be constructed to withstand saturation
from flood waters or the impact of them and protected with vegetation capable
of withstanding flood waters, or shall be constructed of materials that will
resist such a flow. Designs for meeting this requirement must be certified by a
registered professional engineer or architect.
5. These
regulations do not imply that land outside the areas of special flood hazard or
land uses permitted within such districts will be free from flooding or flood
damages. These regulations shall not
create liability on the part of the Town of Hinesburg or any town official or
employee thereof for any flood damages that result from reliance on these
regulations or any administrative decision lawfully made there under.
This motion was seconded by Wayne
Burgess and also passed unanimously.
3. AYER – FINAL PLAT Raymond Ayer was present with George Bedard
to present for final plat review a 2-lot subdivision. Lot #1 is 2.06 acres in size and located on the Hines Road and lot
#3 on the plan is 2.01 acres in size and accessed by a private
right-of-way off the Gilman Road. Due to the
lateness of the evening, it was decided by the DRB members to have Raymond
and George present information on the Hines Road lot to
identify which issues need to be addressed. These lots had
received preliminary plat approval with conditions at the 4/16/02 meeting
of the DRB. After a
presentation by George and questioning by Board members on the
Hines lot, the following issues were identified as
important to this project:
·
There is landscaping
to the north of this lot on the
golf course side and it was discussed whether there should be
landscaping closer to the house within the building envelope. Ted stated that there is
HINESBURG
DRB
Minutes of 8/20/02 Page 5
of 5
extensive farmland next to this lot and a
commercial golf course, so screening is an important issue.
·
This house
lot needs to be marked as out-of-bounds for the golf course.
·
The
drilled well will have to have a yield a specific
number
of gallons per day to meet State
regulations.
·
The new
well will have to be located to ensure that its isolation distance remains on
property owned by the applicant.
·
The
applicant will have to obtain permission from the Select Board to locate the
utility lines under the Hines Road.
·
It was
decided that the language regarding the “right to
farm’ provided by Marian White from the State Agricultural
Department
was more inclusive and should be used on the
plat and in the deed language.
Tom McGlenn made the motion to continue the Ayer
public hearing to the September 3, 2002 DRB meeting at beginning at 7:30 p.m.
in the Town Hall. This motion was
seconded by Ted Bloomhardt and passed with Clint Emmons voting against it.
The
meeting was adjourned at 11:10 p.m.
Respectfully
submitted,
Holly
Russell, Recording Secretary
HINESBURG DEVELOPMENT REVIEW BOARD
ERNEST & THERESA GIROUX
6-LOT SUBDIVISION
MECHANICSVILLE ROAD – MULBERRY LANE
SUBDIVISION CONDITIONS OF APPROVAL
The
Hinesburg Development Review Board hereby grants final plat approval and
approval for development on a private right of way to Ernest and Theresa Giroux
(Barone
Construction Inc.) for a six-lot single family Planned Residential Development (including Site Plan Approval) with 2
Common Areas of a 65 acre parcel of land owned by Ernest and
Theresa Giroux located on the east side of the Mechanicsville
Road. This
approval is also for a Conditional Use Permit to
allow the applicants to move the Village and Rural Residential District boundaries lines per Section 1.3
of the Hinesburg Zoning Bylaws. The subdivision shall be as shown on plans
prepared by O’Leary-Burke Civil Associates, PLC entitled
“Context Map” Sheet #1 and dated 5/1/02 and Sheets #2-6 dated
4/24/02 and revised 6/17/02; and a survey entitled AProperty
Plat 7-lot Subdivision@ by George
Bedard and dated June 19, 2002. This approval is based on Findings of Fact
and subject to the following conditions:
1. Utility
lines shall be placed underground as required in Section 7.9.1 of the
Subdivision Regulations and depicted on Sheet 2 of the Plat.
2. The lots
shall not be sold or a zoning permit issued for building construction until a
Subdivision Permit from the State Division of Wastewater Management is
obtained.
3. All
exterior lighting shall be installed or shielded in such a manner as to
conceal light sources and reflector/refractor areas from view from points
beyond the lot.
4. All structures
shall be located within the appropriate envelopes as depicted on the plat.
5. A roadway
serving more than one house is proposed.
The road shall be built in accordance with the plans submitted
and approved by the Development Review Board. The Association (Mulberry
Lane Homeowner’s Association, Inc, a Vermont non-profit
corporation) shall be as per the submitted and approved “Declaration
of Covenants, Conditions and Restrictions of Mulberry
Lane” be responsible for:
(i)
The Association shall be responsible for
maintaining, repairing, replacing and plowing the roadways, and any parking
areas depicted on the Plan, unless and until they are accepted by the Town…
(ii)
The Association shall maintain all drainageways and
swales upon the Property and shall do whatever is necessary to keep such drainageways
and swales free from debris and other material, which might
hamper natural surface drainage.
(iii)
The Association shall
be responsible for any maintenance to the Common Areas, including the water,
sewer and storm drain infrastructure, unless and until such infrastructure is
taken over by the Town of Hinesburg.
6. Before
obtaining a Certificate of Occupancy for the first dwelling on the shared road,
Mulberry Lane, the owner of the land shall require that the contractor or
engineer in charge of road construction submit a letter to the Zoning
Administrator stating that the road has been built in accordance with this
approval and the approved plans.
7. Final Town approval
of the two curb cuts shall be obtained from the Road Foreman prior
to the granting of the first Certificate of Occupancy.
8. The deed
language set forth in the document titled Declaration of Covenants, Conditions
and Restrictions of Mulberry Lane establishes the
method of sharing the maintenance, repair, snow plowing and any other
Mulberry
Lane Subdivision
Conditions of Approval Page 2
expenses
for the common portion of the roadway are approved and shall
be included in all lot deeds.
9. Before
obtaining a Certificate of Occupancy for the first dwelling, the owner of the
land shall obtain a letter from the power company and submit it to the Zoning
Administrator stating that the utilities have been installed in accordance with
the approved plans.
10. "Substantial
Construction" for this subdivision shall consist of the construction of
the access road to the standards of the plans submitted for it. In accordance with Section 8.9 of the
subdivision regulations, if substantial construction has not been
completed within 3 years from the date of this approval,
final plat approval shall expire.
11. In
accordance with State Statute, the mylar of this subdivision and a copy of the
conditions of approval shall be recorded in the Hinesburg Land Records within
90 days of this approval.
12. Any design
changes from the approved plat of the utility lines or sewage
system shall be approved by the design engineer, and the
Zoning Administrator shall be notified of such. Minor
changes in the position of the utility or sewer system elements to avoid
unforeseen problems shall not require Development
Review Board approval
as long as the design engineer has been
notified.
13. As-built
drawings of the sewage system, or the original drawings, certified by the
engineer to be the as-built, shall be submitted to the Zoning
Administrator before the Certificate of Occupancy is issued for the last
structure is constructed.
14. The owner
of Lot #3 shall be responsible for the maintenance and replacement of the cedar
trees indicated on the approved plan for
screening.
15. All blasting
shall be done per a submitted document from Rockaway Drilling and
Blasting, entitled Blast Plan for the Mechanicsville Road and
neighbors shall be notified one week prior to
the time this will occur.
16. The areas
exposed during construction shall be treated in a manner consistent with the
procedures contained in the Vermont Handbook for Soil Erosion and Sediment
Control on Construction Sites.
17. No further
subdivision of this property shall occur without review and approval of the
Hinesburg Development Review Board.
18. The mention
of additional units in the covenants and other
submitted legal language does not indicate acceptance
of the possibility of this occurring until, and at such point as the necessary
permits have been obtained and any language included in the covenants and other
legal documents submitted with this application have been reviewed
to reflect the new application.
19.
An Irrevocable Offer of Dedication shall be made to the Town
of Hinesburg for the road serving this subdivision and included as part of this
approval.
20.
Landscaping shall be provided as per the approved
plan including street trees shall be planted an average
of but no more than 40 feet apart on Mulberry Lane, on
the north side except where planted with cedars, and on the
south side beyond the hammerhead. Such
plantings shall meet the requirements of Section 7.4 of the Subdivision
Regulations and shall remain the responsibility of the Mullberry Lane
Homeowners Association to maintain in good health or replace
within the next growing season with trees meeting the original requirements.
Mulberry Lane Subdivision Conditions of Approval
Page 3
21. The
installation of the sidewalk along Mechanicsville Road shall be triggered by any of
the following four triggers:
(i)
When the installation
of a sidewalk is a
requirement of the subdivision of the Leggett
property to the south, and/or
(ii)
if
Mulberry Lane is extended for further development, and/or
(iii)
when 10
units of the second phase condominiums have been constructed, or
(iv)
when the
Town of Hinesburg takes over Mulberry Lane as part of public
infrastructure.
These sidewalks
shall be
installed by the developer within 3 months of, or the
next construction season after, the
trigger is activated. This sidewalk, once constructed, will be
maintained by the Town of Hinesburg.
22. The
installation of the sidewalks along Mulberry Lane will be triggered when
Mulberry Lane is extended for further development and/or when 10 units of the
second phase condominiums have been completed and/or when the Town of Hinesburg takes over
Mulberry Lane as part of public infrastructure. These sidewalks shall be
installed by the developer at the time the trigger is activated. These sidewalks shall be maintained by the
Mulberry Lane Homeowners Association until such time as
the Town of Hinesburg takes over
Mulberry Lane.
23. The
sidewalk on the Mechanicsville Road shall be constructed in the proposed 20’ sidewalk
easement. Sidewalks constructed
along the Mechanicsville Road or along Mulberry Lane shall be
concrete, 5’’ deep (6” deep across driveways) five feet wide on a compacted
layer of crushed gravel.
24. On the
areas designated as Common Lands on the approved plans, and as per
Article
III, A (vii) of the Protective Covenants: There shall be
no removal, destruction or cutting of trees or plants on the Commons Land
without the express written consent of the Board and no clearing of trees on
the Common Land other than the removal of dead trees
certified by an arborist.
25. Banks
shall either be at the angle of repose appropriate for the soils of the bank,
and also one that will support vegetation and resist erosion as established by
an engineer or other qualified consultant or if blasted ledge or terraced
not creating a wall over 6’ high.
28. The hours
of construction shall be 7:30 a.m. to 5:00 p.m. Monday
through Saturday.
This
subdivision has been approved as a Planned Residential Development with Site
Plan Approval and the following sections of the Hinesburg Zoning Bylaw have
been waived:
1. Section
3.4.5allowing an additional road-cut onto a Town road
within the Village District to protect a wetland.
2. Section 3.4.5(5) to allow
for the sidewalks to not be constructed prior to the
lots being sold and built on, but the developer will meet the “trigger”
schedule described in the conditions of approval.
3. Sections 3.4.5(3)
and 2.5.1 will allow the garage setback to be
reduced on lot #1 to allow for more usable backyard.
This
subdivision has also been granted a Conditional Use Permit as a
Planned Residential Development to reduce the lot sizes in the Rural
Residential District and to shift the Zoning Line between the Village and Rural
Residential I Districts to create
a village type setting.
_____________________________________ ____________________
Tom
McGlenn, Chair
Date
Hinesburg
Development Review Board
GIROUX/BARONE
SIX-LOT
SINGLE FAMILY
FINDINGS
OF FACT
This
subdivision has been approved based on the fact that it meets the planning
standards of the Hinesburg Subdivision Regulations. This approval was for a Planned Residential
Development and included Site Plan Approval.
6.1.1 –
Suitability for
Development: The land
proposed for subdivision is suitable for development at the density and
configuration proposed. There are no
significant impediments to development that could be harmful to the safety,
health and general welfare of the present or future inhabitants of the subdivision
and/or its surrounding areas.
Road and/trail connections to
Lavigne Hill Road, the Quinn land to the north, and the Russell land to the
south appear to be possible through this property and should be part of the
discussion in future phases.
6.1.2 –
Natural Features Protection: There is a stream with associated wetlands
located east of Lot #6 and other isolated wetlands on Lot #6 and another
running parallel to the Mechanicsville Road on lots #1 and 2. The applicant’s wetland consultant has
flagged the wetlands and identified them to be Class III wetlands, not subject
to the State Wetland Rules.
6.1.3 –
Cultural Features
Protection: There are no major scenic or historic
features of this site. As per this section
of the Subdivision Regulations subdivisions in village areas should focus on
creating “compact, historic, pedestrian-oriented settlement patterns.” This proposed subdivision generally fits the
historic pattern specified in the regulations.
The building envelopes are located in such a way that the buildings will
line up along the road. There are also
proposed sidewalks that will eventually connect this subdivision to Town
sidewalks. The
exposed foundation on lot #3 shall be minimized with plantings.
6.1.4 – Open Space
and Recreation: This
Planned Residential Development includes two blocks of common land totaling
2.96 acres. This commons land protects a portion
of the wetlands east of Lot #6 and the existing clump of trees west of lot
#5. Deed language has been provided for
the management of this common land.
6.1.5 –
Compatibility with Surroundings: The proposed density, building sizes,
pattern of development, and configuration of lots appear to be compatible with
the surrounding properties, and the natural and built environment. There has been a blasting plan submitted and
approved that includes notifying the adjacent
landowners and limiting the hours that blasting shall occur.
6.1.6 –
Transportation: Access to
five of the lots shall be by a 22’ wide, 500’ long road with a hammerhead
turn-around. Lot #2 shall be accessed
directly from the Mechanicsville Road.
These road-cut onto the Town road have been approved by the Select
Board. the project will not create an
unsafe condition on the Mechanicsville Road
and Mike Anthony, Road Foreman, reports that the site
distances at the proposed road cuts are good.
The proposed layout of the road
provides appropriate access to the project and possible future projects on the
property. The road location may be able
to link Mulberry Lane to the existing private road that could serve Phase II
and/or possible a future connection to
adjoining properties as well as to the Lavigne Hill Road.
Included in this approval is a
waiver from Section 3.4.5 of the Zoning Bylaw to allow for two road-cuts within
the Village District for this project.
6.1.7 –
Soil Erosion and Stormwater Runoff: Drainage from
the proposed development road is proposed to flow down to the
Mechanicsville Road and north in front of the property
to the north and eventually to the Canal. Detailed erosion control measures are
proposed and meet the minimum specifications for roadside ditches in the
Hinesburg Policy for Transportation Construction and Improvements.
Giroux/Barone
Finding of Fact
Page 2
6.1.8 –
Water Supply: This
project shall be connected to the municipal water system and at this time the
Town water supply has sufficient capacity to serve this project.
6.1.9 –
Wastewater Disposal: The Select
Board has approved sewer allocations for these 6
single-family units in this project.
6.1.10
– Agriculture/Forestry: This land has not been in use for
agriculture for many years and the land is located in or near the village. No agricultural operations
are taking place on adjoining land (except the Russells’ sugaring) that would
be impacted by this project and there are no significant forest stands on the
portion of the site to be developed.
6.1.11
– Municipal Services: This project is not likely to place an
unreasonable burden on the ability of the town to provide services if the
road is constructed to Town standards and maintained privately. Deed provision have been presented and approved
for the road’s maintenance and snow plowing so that the
properties can be accessed by emergency vehicles year-round.
6.1.12
– Energy Conservation: This parcel of land is orientated so that
it precludes the use of solar energy.
The village location and the provision of sidewalks will give residents
the option of walking instead of driving for errands in the village and/or the
high school.
7.3 –
Outdoor Lighting: No street
lights are proposed or required and any lighting
on the lots will meet the requirements for shielded exterior lighting.
7.4 and
7.5 – Shade Trees and Landscaping: Hardwood street trees of a sufficient size and a
cedar hedge along the northern boundary to provide some screening for the
adjoining property have been proposed and accepted.
7.9 –
Utilities: All utility lines shall be underground.
The
subdivision has been approved as a Planned Residential Development under
Section 4.5.1 of the Hinesburg Zoning Bylaw and the following waivers were
granted:
1. Under
Section 3.4.5, an additional road-cut onto a town road within the
village district to protect a wetland.
2. Under
Section 3.4.5(5), the sidewalks will not be constructed prior to the lots being
sold and built on but meet the “trigger’ schedule described in the conditions of
approval.
3. Under
Sections 3.4.5(3) and 2.5.1 the
garage setback is reduced to allow for more usable backyard.
This
subdivision has also been granted a Conditional Use Permit as a Planned
Residential Development to reduce the lot sizes in the Rural Residential
District and to shift the Zoning District Line between the Village and Rural
Residential I Districts to create a village type setting.
1.
1..
1.
- deed restriction on common land
re tree cutting
- austrian pine vs. ??????
- 8' drop on lot 2 vx walkouts etc. and russ going with the lay
of the land etc.
- russ offered to limit the height of the
access buildings to the ELEVATION of the primary structure
- be sure that the PRD deals
with any possible non complying creations