TOWN OF
DEVELOPMENT REVIEW BOARD MINUTES
Approved
DRB Members Present: Ted Bloomhardt, Lisa Godfrey, Tom McGlenn, George Munson, Dennis Place, Zoë Wainer, Greg Waples.
DRB Members Absent: None.
Also Present:
The meeting began at approximately
Minutes of the
Zoë MOVED to approve the meeting minutes as amended. Lisa SECONDED the motion. The motion PASSED 7–0.
Preliminary Plat
Review – 3-lot/2-unit Subdivision –
[DRB
members: Ted Bloomhardt, Lisa Godfrey, Tom McGlenn, George Munson, Dennis
Place, Zoë Wainer, Greg Waples]
John Kiedaisch spoke on behalf of the HLT. He explained changes from Sketch Plan review:
-
The small lot proposed for the north side of the large
parcel off
- The building lot to the north remained the same.
- The large lot was made even larger, to encompass the lot that was eliminated and also to include a portion of land north of the Town access easement that was originally going to the Town. The Town will now retain about 4 acres.
-
The vehicle ROW to the
-
A public walking/skiing path will now be further to the
north around the edge of a field.
John said the plan
is now to share the Cornish driveway to access the house site on
Lisa asked how large
the building envelope on
Ted MOVED to close
the public hearing and approve the draft decision as written (approval). Tom SECONDED the motion. The motion PASSED 7-0.
[Voting
members: Ted Bloomhardt, Lisa Godfrey, Tom McGlenn, George Munson,
Hart Hill Designs, LLC – Final Plat Review – 9-lot/8-unit
or 8-lot/7-unit PRD/Subdivision - Route 116 –Applicant: David Carse/Hart Hill
Designs, LLC
[DRB
members: Ted Bloomhardt, Lisa Godfrey, Tom McGlenn, George Munson, Dennis
Place, Zoë Wainer, Greg Waples]
Paul Boisvert, an
engineer with Engineering Ventures, spoke on behalf of the applicant. He first reviewed two plans – the original
approved during the Preliminary hearing and an updated version in which building
Lot 2 was replaced with a stormwater retention pond and changes were made to
the interior road. He explained the
applicant hoped to replace the lost house lot with another to the south,
bringing the project back up to a 9-lot/8 unit PRD proposal. He described the project: the entire parcel
is 40+ acres; the subdivision is planned on approx. 5 acres with the remainder
to be kept in agricultural use. Building
lots will have onsite individual wells; well testing has been done with sufficient
yields found. Lots will have individual
septic systems with a shared septic field; the project is in the process of obtaining
wastewater permits. It has also received
approval from VTrans for the Route 116 road cut, which will be 25 feet wide
coming into subdivision.
Paul introduced the
third plan in which a new
Alex thought the
subdivision design would flow more logically and better preserve views if the
new lot were placed at the end of the interior road (to the southwest). The
Alex suggested
placing stakes at the proposed new lot lines for DRB members to review on their
own. David suggested creating a covenant for the eighth lot that required it to
be a one-story house. Ted said the reason
Lots 4 and 5 were moved (from previous plans) was to preserve the view. Tom thought Lots 4, 5 and 8 should relate to
each other, that
Ted asked about the farm
access road. Tim Ballard said it was an
established road, providing the best way to get to the barn throughout the
year. Ted asked if it could shift a
little; Tim said another road could be used to access the barn but it had to
cross a wet area.
Tom MOVED to
continue the hearing to the March 3rd meeting. George SECONDED the motion. The motion PASSED 7-0.
[Voting
members: Ted Bloomhardt, Lisa Godfrey, Tom McGlenn, George Munson,
Dam - Final Plat Review – 7-lot/6-unit PRD –
George Bedard and Joe
Fallon spoke on behalf of the applicant.
George B. passed out a copy of the staff report to which he had added responses. He described the project as a 6-lot PRD with
5 building lots;
He discussed the
concerns regarding a forest management plan.
He said a management plan had been submitted with the DRB application in
August 2008. That plan was the one
currently being used as part of the state current use program. George B. said it has since been revised by the
A. Johnson Company (a forest products business located in
Regarding the state
mapped deer yard, George B. said Tom Yager found no evidence of a deer yard,
that the area in question had never been ground-proofed. George B. said the woodland lot would remain
untouched to grow trees under the management criteria of the current use
program and in accordance with state “Acceptable Management Practices”; he said
those practices deal with how streams and wetlands are treated. He said the applicant planned to cut on a
regular basis as this encouraged new forest growth and provided feed for
wildlife. He added that
Tom McGlenn asked if
the management plan covered 48 acres or 34; Tom Yager said he has broken out management
areas with the 34 acres portion located in the upper area of Area 1. He said areas are based on types of tree stands,
divided either topographically or biologically.
Joe Fallon asked Tom Yager to address the deeryard, stream and erosion
issues. Tom Y. said the rules of the current
use program must be followed regarding erosion or sediment. He said a 4-foot high ring of trees was found
in the area of the deeryard. He remarked
this to be unusual as regrowth is not typically that high if deer are eating
it. He said the area was previously
mapped because of the softwood stand on the WMA but that it was never checked
again. He thought most of Hinesburg’s deeryards
were located in the
Tom Y. said he made cuts
on the parcel in 1992 and 1994, then again just after Dams bought it. Lisa
asked about the documents that have been signed and sent, whether those were
more detailed. Alex said those documents
included the text copy they received tonight plus a mapped plan. He explained that Mike Snyder is waiting to
receive copies signed by the Dams and will then put his own signature on documents.
George B. asked the
board to accept the plan from A. Johnson as the forest management plan requested
as part of the subdivision application. Ted
asked if the plan would be carried out whether the land was in the state
program or not. George B. said yes; he
explained the use program as having a lien attached to it; landowners have to
abide by their plan even if they withdraw from the program. He said a landowner can withdraw and not have
a change of use and not pay the lien OR a landowner can withdraw and pay a
certain amount of money. He said enrollment
was voluntary but once lien is in place, the owner is bound to the terms.
George B. responded
to other issues raised in the staff report:
#2 re: pins being
set. He said the Dams have not had the
surveyors set pins, pending final approval, but that they would be set in the
spring and pins would be reflected on the mylar that is filed. He added that there would be blazing on trees
to mark off the 34-acre protected area.
#3 re: utilities
going under roadways. He said the
applicant has no problem with a condition requiring the installation of
infrastructure before the installation of fabric.
#5A re: necessary infrastructure and the issuance
of a CO for individual building lots. George
said the applicant would follow necessary building permits procedures. He noted that a bond is not being called for as
there is no risk to the town, and that it is not unusual for lots to be presold
before infrastructure is in place as those sales are often the source of construction
funding. Peter Erb said he simply wants
buyers to be aware they will not get a CO until the infrastructure is in. The
group discussed whether this was different from other applications. Peter said there is an expectation that the
developer put in the infrastructure before the lot is sold; he is asking this
expectation to be formalized. Greg thought
perhaps there should be a plan for the event of a landowner not doing the infrastructure. Peter asked only for the deed to make it clear
to the landowner if for whatever reason the developer does not put it in the
infrastructure, he will not get a CO.
George said the applicant would not be opposed to such deed language. The group confirmed they were discussing and
agreeing to bold type under 5A in the staff report.
#5B re: road
maintenance/repair by the owners of
(Beginning pg. 6) Declaration
of Covenants notes to be included:
#1.George said underground power would be put in under the supervision of
GMP who would end up owning the system.
#2. George said prior subdivision approvals have allowed people to clear trees
out to 75 feet. He noted which proposed
lots were wooded and likely to have clearing.
Peter thought prior approvals have not allowed for a specific
measurement of allowed clearing, only that clearing be done within a building
envelope. Lisa said she wished to review
what has been done in the past.
#3. Peter said he wished to speak with Joe Fallon to make sure
#4. George agreed to a condition that increased an asphalt apron from 4’
to 20’.
Ted wanted a clear
statement of direction by the board regarding the amount of land reserved for
the current PRD, whether the 34 acres (25% of the entire parcel as required in
a PRD proposal) was all that ever needed to be set aside regardless of how many
times the landowner came in for future subdivisions. George said this issue was discussed when the
application was first submitted. He said
the landowner has satisfied the minimum requirement of the present subdivision
regulations, but will defer to future subdivision rules should they wish to
propose an amendment to their PRD. Ted thought
there should not be an expectation that no more land needed to be set aside in
any future request for development.
Tom MOVED to
continue the hearing to the February 17th meeting. George M. SECONDED the motion. The motion PASSED 7-0.
[Voting
members: Ted Bloomhardt, Lisa Godfrey, Tom McGlenn, George Munson,
Tom MOVED to go into
deliberative session (
Other Business
Burnett Amendment to
a Conditional Use Permit
Decision: Zoë MOVED to approve the draft decision as amended (approval). Lisa SECONDED the motion. The motion PASSED 7-0.
[DRB
members: Ted Bloomhardt, Lisa Godfrey, Tom McGlenn, George Munson, Dennis
Place, Zoë Wainer, Greg Waples]
Fritz Subdivision
Decision: Zoë MOVED to approve the draft decision as amended (approval). Lisa SECONDED the motion. The motion PASSED 6-0, with Greg abstaining.
[DRB
members: Ted Bloomhardt, Lisa Godfrey, Tom McGlenn, George Munson,
The meeting ended at approx.
Respectfully Submitted:
Karen Cornish
Recording Secretary